98 Tunba Court, Cooroy Mountain
Site Entry Terms & Requirements
Before entering this site, please read the following terms and submit the form at the bottom of this page prior to entry.
Project Details:
Job Name: 98 Tunba Court, Cooroy Mountain
Project Description: General renovation
Principal Contractor: Built by Athena (Athena Services Group Pty Ltd)
Local Authority: Noosa Council
Internal and external renovations including:
- New kitchen cabinetry
- New bathrooms and laundry, including tiling and fixtures
- Internal and external painting
- Timber deck renovations
- Swimming pool renovations
- Roof restoration works
2. Services on Site
Electrical
- Switchboard upgrade required
- Replace lights where needed
- Hard-wired appliances (oven, cooktop, dishwasher)
- Temporary isolation required during works
Plumbing
- Removal and replacement of:
- Toilets
- Vanities
- Showers and floor wastes
- Waterproofing to wet areas (AS 3740 compliant)
Water
- Temporary isolation during bathroom/kitchen works
Stormwater
- No new stormwater works noted (internal refurbishment only)
3. Site-Specific Risks & Controls
Key Risks Identified
- Internal demolition works
- Silica dust from tile removal and cutting
- Manual handling of tiles, cabinetry, appliances
- Electrical works
- Plumbing works and temporary water isolation
- Slips, trips and falls from:
- Uneven surfaces
- Removed floor finishes
- Wet areas during waterproofing
- Falling objects during demolition and overhead works
- Confined internal work areas
Controls
- All demolition as per SWMS
- Dust suppression and silica controls (cutting wet, PPE)
- Exclusion zones during demolition
- Isolation of electrical and water services prior to works
- Manual handling aids and team lifts
- Temporary edge protection / controlled access to balconies
- Clear access paths maintained
- Daily site clean-up
4. Other Site Conditions
- Steep driveway caution
- Respect for neighbours required at all times
5. Amenities
- Toilet provided on site
- First aid kit on site
- Fire extinguisher on site
6. Minimum PPE
- Steel cap boots
- Safety glasses
- Task-specific PPE as required (hearing protection, respirators, gloves)
7. Key Terms of Entry
- Site induction required (QR code)
- Follow SWMS at all times
- Report all incidents, near misses and injuries to Site Supervisor
- Keep site tidy – rubbish to skips provided
- No unauthorised access
- Respect neighbours and common property